How to Assess the Financial Stability of an Advanced Reactor Developer, and How It Relates to the Ability to Deliver on a Long-Term Power Contract
Judge an advanced reactor developer on whether it can fund itself to your contract's first delivery date, not on its reactor design. Check four things in order: cash runway against the next licensing milestone, how much of its capital is committed rather than conditional, which entity signs your contract, and what credit support stands behind that entity.

Key takeaways
- A long-term power contract with an advanced reactor developer is only as strong as the developer's ability to survive until first power, which is usually five or more years away.
- The fastest disqualifier is a short runway: less than 12 months of cash, or an auditor's going-concern doubt, means the company is negotiating for survival, not for your contract.
- Committed capital and conditional capital are different things. Count only money that is signed, funded, and not tied to milestones the developer has not yet reached.
- Ask who signs the contract. A power purchase agreement signed by an unfunded project company with no parent guarantee gives the buyer very little.
- The rubric below scores eight areas out of 100, with hard red flags that cap the score regardless of how good everything else looks.
Why the developer's finances matter more than the reactor
When you sign a power purchase agreement (PPA) with an operating plant, you are buying electricity. When you sign one with an advanced reactor developer, you are buying a promise that a first-of-a-kind plant will be licensed, fueled, financed, and built on schedule. The technology can be sound and the contract can still fail, because the company runs out of money, the price rises past what buyers will pay, or the counterparty that signed your contract never had the means to deliver.
The buyer's real exposure is usually not price. It is time. If the developer stalls, you lose years of planning against capacity that never arrives, and you may have turned down other supply to wait for it.
That is why we assess advanced reactor developers the way a lender would: follow the cash, then follow the contracts.
Three cases that show what can go wrong
Subscription and price risk: NuScale and UAMPS. The Carbon Free Power Project planned six NuScale small modular reactors at Idaho National Laboratory. In January 2023, the project's target power price rose to $89 per MWh, a 53% increase from the earlier $58 estimate. The project had a $1.35 billion DOE cost-share award and an NRC-certified design, yet UAMPS and NuScale agreed to terminate it in November 2023 because it was unlikely to reach enough subscription. The lesson for buyers: a price in a term sheet is an estimate until the cost estimate behind it is mature, and other buyers leaving can sink a project you are still committed to.
Developer solvency: Ultra Safe Nuclear. Ultra Safe Nuclear Corporation, a well-known microreactor and fuel developer, filed for Chapter 11 in October 2024, including its project development subsidiary in Canada. The filing came in the same month that Amazon and Google announced major advanced nuclear commitments. Market enthusiasm does not fund an individual company's burn rate.
Vendor balance sheet: Westinghouse. Large established vendors are not immune. In March 2017, Westinghouse filed for Chapter 11 after it became clear it would book a $6.1 billion write-down for cost overruns on four U.S. reactors it was building. A fixed-price construction commitment is worth only what the company behind it can absorb.
What stronger positions look like
The developers furthest along pair capital with regulatory and commercial milestones that reinforce each other.
- TerraPower closed a $650 million raise in June 2025, with investors including Bill Gates, HD Hyundai, and NVIDIA's venture arm. In March 2026, the NRC issued the construction permit for its Natrium reactor in Kemmerer, Wyoming, the first for a commercial non-light-water power reactor. It still needs a separate operating license.
- Kairos Power received NRC construction permits for Hermes 2 in November 2024. In August 2025, TVA signed a PPA to buy up to 50 MW from Hermes 2, scheduled to begin operations in 2030, under Kairos's 500 MW agreement with Google.
Neither example removes construction or first-of-a-kind risk. They show the pattern a buyer should look for: money, permits, and named customers that line up with the same delivery date.
The rubric: eight areas, scored out of 100
Score each area 0 to 3 using the evidence anchors below. Multiply each score by its weight divided by 3, then add the results. Every anchor is tied to a document you can request or a public record you can check, so two reviewers working from the same evidence should land on the same score.
1. Liquidity and runway to the next milestone (weight: 20)
This is the most important area because every other risk takes time to resolve, and time costs cash.
| Score | Evidence |
|---|---|
| 0 | Less than 12 months of cash at current burn, or the latest audit raises substantial doubt about the company's ability to continue as a going concern |
| 1 | 12 to 24 months of cash, with no committed funding for the next major milestone |
| 2 | More than 24 months of cash, or fully funded through the next licensing milestone |
| 3 | Fully funded through construction permit and the first unit's investment decision, with committed capital in hand |
Ask for: the latest audited financial statements, interim statements, monthly burn, and the board-approved budget to the next milestone. Under PCAOB AS 2415, auditors of public companies must evaluate going-concern doubt, so read the audit opinion and its notes, not just the press releases.
2. Quality of capital commitments (weight: 15)
| Score | Evidence |
|---|---|
| 0 | Funding is mostly announced intentions, memoranda of understanding, or awards with no funded portion |
| 1 | Some committed equity, but most of the plan depends on future raises or conditional awards |
| 2 | Committed equity from several independent sources, plus government awards with a funded share already drawn |
| 3 | Committed capital covers the first plant's development budget, and strategic investors have committed at the project level, not only the corporate level |
Watch for: government awards described in full when only a share is appropriated or drawn, and investments that release only after milestones the developer has not reached. Count those as conditional.
3. Path to project financing (weight: 15)
A developer's corporate cash pays for engineering and licensing. A plant is built with project equity and debt, and that money arrives only when the project can be underwritten.
| Score | Evidence |
|---|---|
| 0 | No cost estimate for the first plant, or no stated plan for construction financing |
| 1 | An early, order-of-magnitude cost estimate and a financing plan without named capital sources |
| 2 | A detailed cost estimate tied to a design and site, with named sources for project equity and debt |
| 3 | Term sheets or conditional commitments for construction financing, and a clear allocation of cost overrun risk |
Ask for: the class of the cost estimate and its date, who carries overrun risk, and the financing plan by source. The NRC's financial qualification guidance asks construction permit applicants for a construction cost estimate, the sources of construction funds, and financial statements. If an applicant has filed, that material is a useful starting point.
4. Licensing maturity (weight: 15)
| Score | Evidence |
|---|---|
| 0 | No application filed and no meaningful pre-application engagement with the NRC |
| 1 | Active pre-application work, with topical reports submitted |
| 2 | Construction permit or combined license application docketed for the plant that would serve you |
| 3 | Construction permit issued for that plant, with an operating license schedule that fits your delivery date |
Score the plant that will serve your contract, not the company's most advanced project. A permit for a test reactor in Tennessee does not license a commercial unit near your load.
5. Fuel supply (weight: 10)
| Score | Evidence |
|---|---|
| 0 | No fuel contracts, and the design needs fuel that is not commercially available |
| 1 | Letters of intent or government allocations for initial fuel only |
| 2 | Binding enrichment or fabrication contracts covering the first core |
| 3 | Binding contracts across enrichment, deconversion, and fabrication for the first core and early reloads, with dates that match the plant schedule |
This matters most for designs that need high-assay low-enriched uranium (HALEU), where domestic supply is still being built. We covered why fuel supply belongs on the financing critical path in our analysis of the X-energy and Centrus HALEU agreement.
6. Customer book and offtake quality (weight: 10)
| Score | Evidence |
|---|---|
| 0 | Announced pipeline consists of non-binding memoranda of understanding |
| 1 | One or two binding agreements, with counterparties that are not investment grade |
| 2 | Binding offtake from creditworthy buyers covering a meaningful share of the first plant |
| 3 | The first plant's output is substantially contracted with creditworthy buyers on terms that support debt |
A large pipeline of non-binding interest is a marketing figure. What matters is whether enough of the first plant is contracted for the project to be financed, because you are relying on the same plant as every other buyer.
7. Credit support behind your contract (weight: 10)
| Score | Evidence |
|---|---|
| 0 | Contract signed by a project company with no assets and no parent support |
| 1 | Parent company named, but no guarantee or security |
| 2 | Parent guarantee or letter of credit covering development-stage termination payments |
| 3 | Guarantee or letter of credit sized to your replacement-power exposure, plus delay damages and clear termination rights tied to milestone dates |
This area is the one buyers control most directly. A developer that scores low elsewhere can still be a reasonable counterparty if the contract protects you.
8. Execution team and governance (weight: 5)
| Score | Evidence |
|---|---|
| 0 | No audited financials, and no one on the leadership team has delivered a nuclear or large energy construction project |
| 1 | Audited financials, but limited project delivery experience |
| 2 | Leadership or the construction partner has delivered comparable large projects; independent board members |
| 3 | A track record of delivering nuclear projects, an experienced construction partner under contract, and regular public or investor reporting |
Red flags that cap the score
Some findings override a good total. If any of these apply, cap the score at 39, whatever the arithmetic says:
- The latest audit raises substantial going-concern doubt.
- The company cannot provide audited financial statements.
- Your contract counterparty is an unfunded project company, and the developer will not offer a parent guarantee or letter of credit.
- The power price in your contract rests on a cost estimate with no stated class or date.
- First power is promised within five years for a design whose fuel is not contracted.
How to read the total score
| Score | What it means | Contract approach |
|---|---|---|
| 80 to 100 | The developer can likely fund itself to first power | Firm PPA, with standard delay and termination protections |
| 60 to 79 | Credible, with specific gaps | Firm PPA conditioned on named milestones, such as permit issuance or financial close, by set dates |
| 40 to 59 | Development stage | Option agreement, capacity reservation, or development agreement, not a firm PPA |
| Below 40 | Not ready for a long-term commitment | Stay engaged, but do not plan supply around this developer yet |
The score is a snapshot. Rescore at each milestone in your contract, and make the next commitment depend on the new score.
What we would do before signing
The rubric tells you where the developer stands. The contract decides who carries the gap. Before signing, we would line up three things:
- Milestone conditions. Tie your obligations to dated events the developer controls: construction permit, financial close, fuel contracts, start of nuclear construction. Miss one, and you can walk away without penalty.
- Sized credit support. Ask for a guarantee or letter of credit that reflects the cost of replacing the power if the plant arrives late or never arrives, not a token amount.
- Information rights. Require quarterly financial reporting and notice of any going-concern opinion, missed licensing milestone, or loss of a major investor or customer.
Sharon Creek Ventures works with energy developers and boards on exactly this sequence: which milestone retires which risk, and what capital or contract it unlocks next. See how we think about advanced nuclear project development, or talk with us about a specific developer or contract.
Independence note: Sharon Creek Ventures is not affiliated with any company named in this article. The facts come from public company, government, and trade sources; the rubric and interpretation are Sharon Creek's.
FAQ
What is the single most important number to check?
Cash runway against the next milestone. Divide unrestricted cash plus committed funding by monthly burn, then compare the result to the date of the developer's next major licensing or financing event. If the money runs out first, the developer will be raising capital under pressure, and every other commitment, including yours, is at risk.
Can a private advanced reactor developer be assessed objectively?
Yes, if it will share the evidence. Private companies are not required to publish financials, but a serious buyer can make audited statements, a funding schedule, and the cost estimate a condition of negotiation. A developer that will not share them under a confidentiality agreement has scored itself on several rubric areas.
Does government funding make a developer financially stable?
It helps, but read the terms. Awards are often cost-shared, paid in stages, or subject to future appropriations. The Carbon Free Power Project had a $1.35 billion DOE award and was still terminated when it could not attract enough subscribers. Count only the funded, drawable share as committed capital.
How often should the rubric be rescored?
At every contract milestone, and whenever the developer raises capital, receives an audit opinion, or changes its cost estimate or schedule. A developer's position can change within a single quarter, as Ultra Safe Nuclear's 2024 bankruptcy showed.
Sources
- Nuclear Engineering International — UAMPS and NuScale cancel plans to build SMRs at INL
- UAMPS — Carbon Free Power Project
- POWER — Major Microreactor Developer Enters Bankruptcy Amid Nuclear Industry Surge
- Toshiba — Notice on Chapter 11 Filing by Westinghouse Electric Company
- TerraPower — TerraPower Announces $650 Million Fundraise
- U.S. Department of Energy — NRC Issues Construction Permit for TerraPower's Natrium Advanced Reactor
- NRC — Construction Permit Application Review Documents for Hermes 2
- Kairos Power — Google, Kairos Power, TVA Collaborate to Meet America's Growing Energy Needs
- PCAOB — AS 2415: Consideration of an Entity's Ability to Continue as a Going Concern
- 10 CFR Part 50, Appendix C — Financial qualifications for construction permits and combined licenses